NIIEFA-ENERGO, LLC performs work involved in designing traction and step-down substations with primary voltage of up to 220 kV. The enterprise is a member of non-commercial partnership of the Baltic Association of Designers self-regulatory organization; it has a competency certificate for certain types of works that affect the safety of capital construction projects.
Types of works performed:
-
main circuit design;
-
architectural and building aspects;
-
electric machinery and electric mains location plan;
-
installation of electric machinery;
-
power grounding and lightning protection;
-
relay protection and automation (including coincidence circuits and feature determination tables for shutdown terminals);
-
Automated Process Control Systems;
-
heating and ventilation;
-
lighting;
-
fire alarm systems;
-
ther electrical engineering work (ventilation and fire-fighting automatic systems, etc.);
-
optional equipment assignments for plants.
In working as general designer, NIIEFA-ENERGO uses external subcontracting for the following work:
-
engineering survey;
-
design of overhead and cable lines;
-
water supply and drainage;
-
master plan and transport;
-
other special sections (environmental protection, electromagnetic compatibility, etc.)
Completed design work:
-
Step-down substation 110/10/10 kV Osinovaya Roshcha (Lenenergo) – completely
-
Step-down substation 110/10/6 kV Yusupovskaya No. 109А (Lenenergo) – electrical engineering, parts: relay protection and automation, and auxiliaries
-
Step-down substation 110/10/10 kV Volkovskaya No. 160А (Lenenergo) – electrical engineering (all parts)
-
Step-down substation 110/10 kV Varzuga (Kolenergo) – completely
-
Step-down substation 110/10 kV Olenitsa (Kolenergo) – completely
-
Step-down substation 110/10 kV Kashkarantsy (Kolenergo) – completely
-
Step-down substation 110/10 kV Umba (Kolenergo). Reconstruction – electrical engineering.
-
Step-down substation 110/10/10 kV No. 369А (Lenenergo) – electrical engineering, part: relay protection and automation
-
Traction substation Balakirevo. Reconstruction – electrical engineering
-
Traction substation 110/10/3.3 kV Khrustalnaya – electrical engineering
-
Traction substation 110/27.5/10 kV Remontnaya – electrical engineering, part: relay protection and automation
-
Traction substation 110/27.5/10 kV Kazan – electrical engineering, part: relay protection and automation
-
Traction substation Ussuriysk. Compensation system – completely
-
Traction substation Smolyaninovo. Compensation system – completely
-
OJSC Apatit. Substatons-74, 76. Modernization of rectifier units – electrical engineering
-
Substation 220/6 kV Protvino – completely
-
Traction substation Shcherbinka – electrical engineering
Design Department, NIIEFA-ENERGO, LLC